U-Ditch Supply in LNG Project

Challenge :
A $26M tender for U-ditch supply received only one bid at $55M due to monopolies at every stage of the supply chain.

Solution: Value Engineering

  • Negotiated lower cement pricing
  • Engaged additional concrete suppliers
  • Partnered with Perth supplier for a temporary batching plant
  • Modified design to reduce concrete volume

Outcome
$28M Total Cost Savings
Received two revised bids at approximately $27M, aligning with original budget.